PHOTOS: Julius Berger releases fresh images on progress of 2nd Niger bridge

2 minutes
See all images: https://www.geezgo.com/sps/62058
Julius Berger Nigeria Plc has released fresh images on the progress recorded with the ongoing construction of the 2nd Niger Bridge.

In a report which accompanied the images, the company said as of January 10, 2020, the project had reached a stage of 30.12% completion.

The project is expected to be completed by February 2022. In June, the company launched a website to “allow Nigerians track the status” of the project.

Below are the newly released pictures:
Western Approach – Casting station – Segments 1 and 2 launched

CH 24+000 to 24+500 – Hyraulic dredging into alignment

Amakom Bridge – Bridge deck casted and parapet wall (North) installed
Niger Bridge Axis 260 – Formwork and reinforcement (North)
Culvert and Drains CH 29+510 – Walls and bottomslabs on going

Eastern Approach – Casting station – Lifting beams completed
Soil Improvement CH 31+750 – Laying of Geotextile upper layer

Soil Improvement CH 32+500 – Installation of PVD

Owerri Interchange Axis 50 – Bored piling on going
Join Geezgo for free. Use Geezgo's end-to-end encrypted Chat with your Closenets (friends, relatives, colleague etc) in personalized ways.>>

Post a Comment

[disqus][blogger][facebook]

Kogonuso

Contact Form

Name

Email *

Message *

Powered by Blogger.
Javascript DisablePlease Enable Javascript To See All Widget